Flooding Case Study: Boscastle

Geography: KS3, topic 8.2.4

What Caused The 2004 Boscastle Flash Flood?

On the 16th of August 2004, there was a flash flood in Boscastle (in Cornwall).

Removal of vegetation

Removal of vegetation

  • The removal of trees and vegetation upstream of Boscastle increased surface runoff.
Steep relief

Steep relief

  • Boscastle is in a very steep valley, which means surface runoff is high and fast.
  • The steep valley acted like a funnel, channeling all of the rain into Boscastle.
The low bridge in Boscastle

The low bridge in Boscastle

  • A bridge over the River Valency in Boscastle was not very tall and had a low arch.
  • When the flash flood came, cars and debris became stuck under the arch creating a dam. This led to even worse flooding.
Intense rainfall

Intense rainfall

  • 200mm of rainfall fell in 24 hours (the monthly average was 75mm).
  • Between 50mm and 100mm fell in the space of a few hours.
  • July and August 2004 had been rainy, so there was already a lot of surface runoff.
Lack of flood defences

Lack of flood defences

  • Boscastle had no flood defences. This meant that it was vulnerable to any especially heavy rainfall.

Test yourself on Flooding Case Study: Boscastle

  • When was Boscastle, England last devastated by severe flash floods?

  • How much rainfall did Boscastle get in a period of two hours just before the 2004 flash flood?

Practise this topic for free