3.4.3

Inverse Proportion

Test yourself

Inverse Proportion

3 builders take 12 days to build a wall. How long does it take 4 builders to build an identical wall?

Illustrative background for NotationIllustrative background for Notation ?? "content

Notation

  • We write y α 1x and there is some number k such that y = kx.
  • The time taken to complete a job is inversely proportional to the number of people working on the job.
Illustrative background for Days taken are inversely proportional to buildersIllustrative background for Days taken are inversely proportional to builders ?? "content

Days taken are inversely proportional to builders

  • d = number of days taken.
  • b = number of builders.
Illustrative background for Sub in b = 4Illustrative background for Sub in b = 4 ?? "content

Sub in b = 4

  • We want to know the days taken for 4 builders to build the wall.

Jump to other topics

1Number

1.1Place Value

1.2Factors & Multiples

1.3Operations

1.4Fractions, Decimals & Percentages

1.5Growth & Decay

1.6Measurements & Units

1.7Accuracy

2Algebra

3Ratio, Proportion & Rates of Change

4Geometry & Measures

5Probability

6Statistics

Go student ad image

Unlock your full potential with GoStudent tutoring

  • Affordable 1:1 tutoring from the comfort of your home

  • Tutors are matched to your specific learning needs

  • 30+ school subjects covered

Book a free trial lesson